M62 Motorway, Rochdale to be closed
Date published: 04 May 2006
Junction 21 Improvement Drawing
The M62 motorway at Rochdale will be closed overnight over two weekends while a new bridge is installed as part of junction improvements for the Kingsway Business Park.
The new Dig Gate Lane farm bridge will replace the existing bridge as part of the £5 million remodelling of Junction 21 to improve access for the new development under construction.
The motorway will be closed eastbound overnight on Saturday 6 May from 20.00 until 08.00 while the first section of the bridge deck is lifted into place by a 100 tonne crane.
The following weekend, Friday 12 May and Saturday 13 May further closures are planned for the westbound motorway when the remaining sections of the bridge deck are craned into position. On Friday evening the motorway will be closed from 21.00 until 8.00 and on Saturday evening from 20.00 until 08.00.
A clearly signed diversion will operate via M62 Junction 20, the A627M, Kingsway, Elizabeth Way and M62 Junction 21 for both closures.
Highways Agency project manager Paul Elliott said:
"The motorway closures have been carefully planned and are being carried out overnight and at the weekend to keep delays to a minimum for road users.
"Motorists are however asked to allow extra time for their journey and take extra care while driving through the road works and the diversion, adhering to the speed limits for their own safety and the safety of road workers."
The exit slip roads from Junction 21 have also been reduced to a single lane with a mandatory 30 speed limit to create a safe area for work to be carried out.
The improvements include:
- The construction of a new dual carriageway and two roundabouts between the eastbound exit slip road and the existing A640 (Elizabethan Way) roundabout
- Modifications to the existing eastbound exit slip road
- Improvements to the westbound slip road
As part of the scheme, the subway from the south side of the M62 to Moor Bank Lane will be closed, and the footpath diverted westward towards Dig Gate Lane.
The junction improvements are being overseen by the Highways Agency and paid for by Wilson Bowden Development Ltd and the North West Development Agency is association with Rochdale MBC.
Future motorway closures will be required when the old bridge is demolished, but dates are yet to be confirmed.
Do you have a story for us?
Let us know by emailing news@rochdaleonline.co.uk
All contact will be treated in confidence.
Most Viewed News Stories
- 1£100 booze and off-road bikes warning in Rochdale borough
- 2Historic mill and ‘eyesore’ neighbour will be transformed into almost 300 apartments
- 3AI cameras to catch drivers breaking the law being tested
- 4Rochdale man and his rescue dog to tackle West Highland Way for children's charity
- 5New audio drama features Rochdale's rich canal history
To contact the Rochdale Online news desk, email news@rochdaleonline.co.uk or visit our news submission page.
To get the latest news on your desktop or mobile, follow Rochdale Online on Twitter and Facebook.