Rochdale Road, Firgrove (NEW) - at its junction with Willows Lane
Temporary 3 way signals to facilitate safe access to replace BT pole, 9.30am to 3.30pm
2 May 2012
Promoter: BT Openreach

Oldham Road, Rochdale (NEW) - adjacent to Woodbine Street junction
Temporary 2 way signals to facilitate installation of water connection, 8.00am to 5.00pm
14 April 2012 until 16 April 2012
Promoter: United Utilities

Milnrow Road, Rochdale - at the railway bridge between Chichester Street and Fishwick Street
Temporary 2 way signals to facilitate refurbishments to bridge, 9.30am to 4.30pm
2 April 2012 until 20 April 2012
Promoter: MPT

Manchester Road/Coronation Avenue, Heywood - at the junction
Temporary 3 way signals to facilitate signalisation of junction
24 February 2012 until 15 May 2012
Promoter: Impact

Hopwood Avenue, Heywood - Manchester Road to Alexander Street
Temporary road closure to facilitate signalisation of junction on Manchester Road in conjunction with the works named above
24 February 2012 until 15 May 2012
Promoter: Impact

Todmorden Road, Littleborough - from no 24 to no 56
Temporary signals to facilitate retaining wall reconstruction work at Temple Lane/Todmorden Road
9 January 2012 until 13 April 2012
Promoter: Impact Partnership

Todmorden Road, Littleborough - from no 22 Glen View to no 19 Fair View
Temporary signals to facilitate retaining wall reconstruction work at Todmorden Road
9 January 2012 until 20 April 2012
Promoter: Impact Partnership

Canal Street, Littleborough - adjacent to train station
Temporary 2 way signals to facilitate construction of new platform access ramp
1 November 2011 until 19 May 2012
Promoter: BAM Construction

Drake Street, Rochdale - Smith Street to Water Street
Road closure to facilitate the diversion of various services in relation to Metrolink
3 May 2011 until further notice
Promoter: Metrolink
For further Metrolink information please visit www.rochdale.gov.uk/metrolink

Metrolink Works, Rochdale
Works may be progressing at the following locations:
Maclure Road, Drake Street, School Lane, Richard Street and Smith Street.

Drake Street, Rochdale (NEW) – from no 13 to no 39
Temporary 2 way signals to facilitate electrical diversion works
16 April 2012 until 4 May 2012

Henry Street, Rochdale – near its junction with Maclure Road
Temporary 2 way signals to facilitate works to construct a new turning head
9 April 2012 until 4 May 2012

Faulkner Street, Rochdale – from its junction with River Street to its junction with Smith Street
Temporary one way working from River Street to Smith Street in that direction
21 March 2012 until 18 April 2012

Lower Tweedale Street - No access to Lower Tweedale St via Tweedale St/Milkstone Rd Junction
Temporary prohibition of vehicles to facilitate ongoing Metrolink works
6 February 2012 until 30 April 2012

Maclure Road/Richard Street/Station Road/Hampden Street, Rochdale
Temporary one way working on all above-named streets to facilitate ongoing Metrolink works
1 February 2012 until 31 December 2012

Drake Street, Rochdale – Milnrow Road/School Lane junction
Temporary 3 way signals to facilitate sewer connection work
3 January 2012 until further notice


Road closures and temporary signals affecting non strategic routes

Shore Road, Littleborough (NEW) - adjacent to no 2
Temporary 2 way signals to facilitate installation of water connection, 8.00am to 5.00pm
17 April 2012 until 23 April 2012
Promoter: H2O Water Services

Well'I'Th Lane, Rochdale (NEW) - at the canal bridge
Temporary 2 way signals to facilitate trial hole works, 8.00am to 5.00pm
14 April 2012 until 18 April 2012
Promoter: Electricity North West

Newhey Road, Milnrow - at the railway bridge near Elizabethan Way junction
Temporary 2 way signals to facilitate parapet works to bridge, 9.30am to 3.30pm
12 March 2012 until 22 April 2012
Promoter: MPT

Blair Street/Edenfield Street/Marlborough Street/Preston Street, Rochdale
Temporary prohibition of vehicles on all above-named streets at their respective junctions with Rooley Moor Road to facilitate gas main replacement work
20 February 2012 until 23 April 2012
Promoter: National Grid

Baron Street, Rochdale – from its junction with Livsey Street to its junction with Summer Castle
Temporary one way working from Livsey Street to Summer Castle in that direction
30 January 2012 until 29 January 2013
Promoter: Electricity North West Ltd

Temple Lane, Littleborough - from outside no 1 to its junction with Todmorden Road
Temporary prohibition of vehicles to facilitate the replacement of the existing retaining walls
7 November 2011 until 1 May 2012
Promoter: Impact Partnership

Calderbrook Road, Littleborough
Closed in the Calderdale Area
Until further notice
Promoter: Calderdale MBC

Do you have a story for us?

Let us know by emailing news@rochdaleonline.co.uk
All contact will be treated in confidence.


To contact the Rochdale Online news desk, email news@rochdaleonline.co.uk or visit our news submission page.

To get the latest news on your desktop or mobile, follow Rochdale Online on Twitter and Facebook.